The role of the Dispute Board is to help avoid or resolve disputes within the constraints of the contract and the Dispute Board procedure. It is not there to replace the day to day decision making and management exercised by the Contractor, the Project Manager/Engineer or the Employer. For instance the parties may ask the board to decide a dispute over two drawings that contradict each other. The Dispute Board will decide which of the two drawings reflect the contractual obligations of the parties. The Dispute Board will not tell the parties which drawing should be built because once the dispute board has declared the contractual obligation, if the Engineer wants something else building he can instruct a variation.